Extending horizons

Bangalore International Airport Expansion
Automation of Into Plane Services
Operations & Maintenance

Bangalore International Airport Expansion

Supplementary SPRH Agreement has been executed on 14th October 2010.
Order placed on IOTL for construction of HRS on back to back basis.
Order placed on Skytanking Brussels for consultancy.
Commissioning shall be done by IOSL.
Project funding by IOSL.

Key Dates

Sl No Milestones Key Date
1 Order for Pipelines Procurement 17.12.2010
2 Receipt of Pipelines including Painting / Wrapping Coating etc., 30.04.2011
3 Order for DBBVs 28.12.2010
4 Receipt of DBBVs 30.08.2011
5 Receipt of Pit Valves 02.07.2011
6 Award of Electrical/Instrumentation/Auto Contract 04.12.2010
7 Award of Pipelines Laying Contract 28.12.2010
8 Completion of Pipelines Laying Works 05.09.2011
9 Completion of Electrical/Instrumentation/Automation Works 17.10.2011
10 Testing & Commissioning Completion 26.11.2011
11 As per SSPRH 31-12-2011

Automation of Into Plane Services

Information from the FIDS is integrated to the mobile fueling vehicles. This informations is used by the officer on the tarmac,to ensure real time billing to the suppliers. IOSL has embarked on this mission to automate the into-plane services at both Bangalore and Delhi.

The significant advantages are as follows:

Ready source of data, with no manual writing
Real time data acquisition.
Tracking of vehicular movement
Immediate billing to suppliers
Value Addition to the end consumers

Operations and Maintenance

With respect to handling of the fuelling services in 2 tier and 3 tier cities, several IndianOil Public Sector Companies have offered us the O&M of their airports and the discussions are in the advanced stage.