Extending horizons
Bangalore International Airport Expansion
Automation of Into Plane Services
Operations & Maintenance
Bangalore International Airport Expansion
Supplementary SPRH Agreement has been executed on 14th October 2010.
Order placed on IOTL for construction of HRS on back to back basis.
Order placed on Skytanking Brussels for consultancy.
Commissioning shall be done by IOSL.
Project funding by IOSL.
Key Dates
| Sl No |
Milestones |
Key Date |
| 1 |
Order for Pipelines Procurement |
17.12.2010 |
| 2 |
Receipt of Pipelines including Painting /
Wrapping Coating etc., |
30.04.2011 |
| 3 |
Order for DBBVs |
28.12.2010 |
| 4 |
Receipt of DBBVs |
30.08.2011 |
| 5 |
Receipt of Pit Valves |
02.07.2011 |
| 6 |
Award of Electrical/Instrumentation/Auto
Contract |
04.12.2010 |
| 7 |
Award of Pipelines Laying Contract |
28.12.2010 |
| 8 |
Completion of Pipelines Laying Works |
05.09.2011 |
| 9 |
Completion of
Electrical/Instrumentation/Automation Works |
17.10.2011 |
| 10 |
Testing & Commissioning Completion |
26.11.2011 |
| 11 |
As per SSPRH |
31-12-2011 |
Automation of Into Plane Services
Information from the FIDS is integrated to the mobile fueling vehicles.
This informations is used by the officer on the tarmac,to ensure real
time billing to the suppliers. IOSL has embarked on this mission to
automate the into-plane services at both Bangalore and Delhi.
The
significant advantages are as follows:
Ready source of data, with no
manual writing
Real time data acquisition.
Tracking of vehicular movement
Immediate billing to suppliers
Value Addition to the end
consumers
Operations and Maintenance
With respect to handling of the fuelling services in 2 tier and 3 tier
cities, several IndianOil Public Sector Companies have offered us the
O&M of their airports and the discussions are in the advanced stage.
|